Railway – Risk Profile and Controls |
|
Timing and Duration |
1-Day workshop held in
September 2002 |
|
Client |
Infrastructure, Energy
and Resources |
|
Participants |
Representatives from
·
Federal Hotels and Resorts (Railway
Operator)
·
Contractors
·
Sub-contractors
·
State Government Agencies
·
Technical Advisors |
|
Background |
Construction of the Abt
Railway was approaching completion. There was a need to identify
potential risks that may delay the opening or safe operation of the
railway. The Parties to the Principal Siteworks contract, Hazell
bros Civil Contracting (Contractor) and Infrastructure, Energy and
Resources (representing the Principal), agreed it would be
appropriate to undertake a Risk Workshop to identify key project
risks. |
|
Objective |
To identify the risks associated with the safe
operation and maintenance of the Abt Railway and identify possible
mitigation strategies |
|
Outcome |
·
Critical functions of the risk
strategy were agreed
·
Key risk areas were identified
·
Actions, including an overview of
the risk area, what was to be done, by who and by when, were agreed
to address key risk areas |